

The feasibility study evaluated different combinations of options concerning the
powerhouse positioning, access roads and the waterway layout.
The final option is the following:
Gross Head: 189.05 m
Penstock diameter: 1200 mm
Turbines: 2 Pelton
Installed Capacity: 4.5 kW
Activities Performed:
Feasibility study
Topgraphic Drone Survey
Detailed hydrological analysis
Tender design
Assistance in tender documents.